THE PROGRESS OF CONSTRUCTION OF THE PREMIER RESORT HOTEL – December 2021 - LEV Development

THE PROGRESS OF CONSTRUCTION OF THE PREMIER RESORT HOTEL – December 2021

December 2021
31

In December 2021:

  • Promenade fencing was installed;
  • 70% of the number plates are mounted;
  • Installation of entrance door boxes continues;
  • The screed of the restaurant is filled in;
  • Reception smoke removal systems are installed.
/