In November 2020:
- waterproofing of the entrance group was carried out;
- paving continued;
- installation of sliding systems and restaurant glass continued;
- the glazing of the panoramic elevator has started;
- long preparation for the launch of the heating system;
- installation of glass partitions in bathrooms of number fund proceeds.