Construction progress of the Premier Resort Hotel - February 2021 - LEV Development

Construction progress of the Premier Resort Hotel – February 2021

March 2021
10

In February 2021:

  • Completed the installation of posts under the fence;
  • Installation of partitions on the 0th floor continues.
  • Installation of plumbing and electricity has begun.
  • The laying of ceramic tiles in the rooms continues.