In October 2020:
- long preparation for laying paving, backfilling the site;
- installation of the hotel entrance group and entrance to the parking lot continued;
- the installation of premises for settlement and cash operations continued;
- embedded parts were installed under the fence of the third section;
- installation of insulation and sound insulation of the conference hall continued;
- the installation of double-glazed windows on the commercial floor has begun;
- the installation of the drainage system has been completed;
- the waterproofing of the drainage tray was carried out;
- continued insulation of the stairwell.