IKON Resort Construction Progress – March 2026

March 2026
17

For the attention of investors, a new report on the construction of IKON Resort in Bukovel:

  • The installation of the bar counter in the bright hall restaurant continues;
  • The installation of the iron frame for the terrace on the second floor continues;
  • Installation of partitions between rooms on balconies continues;
  • A drain is being installed between the passage doors between the restaurant halls;
  • Painting of metal structures between the passage doors between the restaurant halls is underway;
  • The protective grille of the restaurant’s freight elevator is being installed;
  • Ventilation grilles are being installed in the restaurant hall;
  • Tile installation is underway in the spa pool;
  • The slats on the hotel balconies are being installed.
/