In June 2021:
- The floor of the 4th floor in section II has been completed;
- Concreting of vertical structures (walls, pylons and stairways) of the 5th floor of Section II continued;
- Installation of the foundation slab of the I section is completed;
- Concreting of vertical structures of the basement (walls, pylons) of the I section has begun.
/