Construction progress of LIFE STORY - December 2021 - LEV Development

Construction progress of LIFE STORY – December 2021

January 2022
06

At the end of December 2021:

Section 1

  • Vertical structures (pylons, walls) of the 13th floor are concreted;

Section 2

  • The floor of the 16th floor has been completed;
  • The masonry of the external and internal walls on the 8th floor has been completed.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT
запис на консультацію