In April 2021:
- Concreting of vertical structures of the basement (walls and pylons) at the mark -4.55 in the second section was completed;
- Performed 50% concreting of vertical structures (walls, pylons) of the 1st floor in the second section;
- Finished the pile field in the first section.
/