At the end of October 2021:
Section I:
- The floor of the 8th floor has been completed;
- 70% of vertical structures (pylons, walls) of the 9th floor are concreted;
- 98% of masonry of external and internal walls of the 3rd floor is executed;
- 80% of masonry of external and internal walls of the 4th floor is executed;
- The installation of ventilation ducts on the 6th floor has been completed.
Section 2:
- Concreting of vertical structures (pylons, walls) of the 12th floor is completed;
- The floor of the 12th floor has been completed;
- 20% of masonry of the 6th floor of external and internal walls is executed;
- 80% of masonry of the 5th floor of external and internal walls is executed;
- 40% of the masonry of the 7th floor of the external walls was made.
/