Construction progress of LIFE STORY - October 2021 - LEV Development

Construction progress of LIFE STORY – October 2021

November 2021
05

At the end of October 2021:

Section I:

  • The floor of the 8th floor has been completed;
  • 70% of vertical structures (pylons, walls) of the 9th floor are concreted;
  • 98% of masonry of external and internal walls of the 3rd floor is executed;
  • 80% of masonry of external and internal walls of the 4th floor is executed;
  • The installation of ventilation ducts on the 6th floor has been completed.

Section 2:

  • Concreting of vertical structures (pylons, walls) of the 12th floor is completed;
  • The floor of the 12th floor has been completed;
  • 20% of masonry of the 6th floor of external and internal walls is executed;
  • 80% of masonry of the 5th floor of external and internal walls is executed;
  • 40% of the masonry of the 7th floor of the external walls was made.
/