In July 2022:
House 1:
- The foundation slab is poured;
- Arranged walls, columns and ceiling “-2” floor;
- The walls and columns of the “-1” floor are 50% finished.
House 2:
- Construction of the pit has been completed;
- Concrete preparation for the foundation slab has been completed.
/