Construction progress of RC ARTHOUSE park - June 2021 - LEV Development

Construction progress of RC ARTHOUSE park – June 2021

June 2021
30

In June 2021:

  • The concreting of the floor slab over the 5th, 6th, and 7th floors of the 1st section was completed;
  • Concreting of vertical structures of 6, 7, 8 floors of the I section was completed
  • The masonry of the external walls on the 1st floor of the first section was completed;
  • The masonry of the external walls on the 2nd and 3rd floors and sections began;
  • Completed masonry of external walls on 4, 5, 6 floors;
  • Reinforcement of vertical structures of the 8th floor of the III section continued.
/