In December 2021:
- The collective smoke removal system in section I is 100% installed;
- Installation of ventilation from apartments in sections I, II and III has been completed;
- The masonry of the interior walls in sections I and II has been completed;
- The masonry of the inner walls on the 10th and 11th floors continues;
- Installation of sewerage pipelines in sections I and III has been completed;
- Installation of electric lighting of common areas in section I has been completed;