Construction progress of RC ARTHOUSE park - July 2021 - LEV Development

Construction progress of RC ARTHOUSE park – July 2021

July 2021
29

In July 2021:

  • The backfilling of the pit in the first section has been completed;
  • All monolithic works in the first section have been completed;
  • The masonry of the external walls on the 4th floor of the first section has been completed;
  • The masonry of the external walls on the 5th floor continued and the masonry of the internal walls on the 2nd and 3rd floors in the 1st section began;
  • Arranged a foundation slab in the second section;
  • Reinforcement and concreting of vertical structures (-2 levels) of the parking lot of the II section continued;
  • The masonry of the inner walls on the 1st and 3rd floors of the III section has been completed;
  • The masonry of the outer walls on the 7th floor continued;
  • The masonry of the inner walls on the 4-5-6 floors of the III section continued;
  • Concreting of vertical structures on the 9-10-11 floors of the III section was completed;
  • Completed concreting of the floor slab over the 9-10th floor;
  • The concreting of the floor slab above the 11th floor continues.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT
запис на консультацію