In July 2021:
- The backfilling of the pit in the first section has been completed;
- All monolithic works in the first section have been completed;
- The masonry of the external walls on the 4th floor of the first section has been completed;
- The masonry of the external walls on the 5th floor continued and the masonry of the internal walls on the 2nd and 3rd floors in the 1st section began;
- Arranged a foundation slab in the second section;
- Reinforcement and concreting of vertical structures (-2 levels) of the parking lot of the II section continued;
- The masonry of the inner walls on the 1st and 3rd floors of the III section has been completed;
- The masonry of the outer walls on the 7th floor continued;
- The masonry of the inner walls on the 4-5-6 floors of the III section continued;
- Concreting of vertical structures on the 9-10-11 floors of the III section was completed;
- Completed concreting of the floor slab over the 9-10th floor;
- The concreting of the floor slab above the 11th floor continues.
/