In July 2022:
Section I:
- The facade arrangement is 40% completed;
Section III:
- Installation of elevators has begun;
- Installation of heating systems on the 10th-11th floor is underway;
- Plastering of the walls on the 8th floor continues;
- Finished plastering of the walls on the 9th floor;
- 60% of the facade walls have been insulated.
/