In August 2021:
- The masonry of the external walls on the 5th floor of the I section was completed;
- The masonry of the external walls on the 6th and 7th floors of the I section continued;
- The masonry of the inner walls on the 4th-6th floors of Section I continued;
- Arranged vertical structures on the -1 floor and vertical structures of the commercial floor of the II section;
- Arranged vertical structures on the 1st floor of section II;
- Concrete slab over -1 level of parking and commercial floor;
- Reinforcement of the floor slab over the 1st floor of Section II continued;
- The masonry of the inner walls on the 4th-6th floors of Section III was completed and continued on the 7-9th floors of Section III;
- Completed concreting of vertical structures on 12-13 floors of section III;
- Concreting of vertical structures on the 14th floor of Section III continued;
- Completed concreting of the floor slab above the 12-13th floor of section III;
- The installation of ventilation ducts on 6-8 floors of Section III and on 5-7 floors of Section I continues.
/