In August 2022:
Section I:
- The insulation of the facade walls has been completed;
- The installation of the elevators has been completed.
Section III:
- The installation of elevators has been completed;
- Installation of heating systems on the 9th floor has been completed;
- The plastering of the walls on floors 7-4 was completed;
- 90% of external sewage systems were installed;
- The insulation of the facade walls has been completed.