Хід будівництва ЖК ARTHOUSE park - Construction progress of RC ARTHOUSE park - - Октябрь 2021[:] - LEV Development (Лев Девелопмент)

Construction progress of RC ARTHOUSE park – October 2021

October 2021
27

In October 2021:

  • The masonry of the internal partitions on the 7th floor of the I section was completed;
  • The masonry of the internal partitions on the 8-9 floors of the I section continued;
  • Arranged insulation of the coating in section III;
  • The waterproofing of the coating in section III continues;
  • The masonry of the external walls on 9-13 floors in Section III was completed;
  • The masonry of the external walls on 14 floors in section III continues;
  • The masonry of internal partitions on 9-13 floors in section III continues;
  • The installation of ventilation ducts in section I was completed.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT