Construction progress of RC ARTHOUSE park - October 2021 - LEV Development

Construction progress of RC ARTHOUSE park – October 2021

October 2021
27

In October 2021:

  • The masonry of the internal partitions on the 7th floor of the I section was completed;
  • The masonry of the internal partitions on the 8-9 floors of the I section continued;
  • Arranged insulation of the coating in section III;
  • The waterproofing of the coating in section III continues;
  • The masonry of the external walls on 9-13 floors in Section III was completed;
  • The masonry of the external walls on 14 floors in section III continues;
  • The masonry of internal partitions on 9-13 floors in section III continues;
  • The installation of ventilation ducts in section I was completed.
/