In October 2021:
- The masonry of the internal partitions on the 7th floor of the I section was completed;
- The masonry of the internal partitions on the 8-9 floors of the I section continued;
- Arranged insulation of the coating in section III;
- The waterproofing of the coating in section III continues;
- The masonry of the external walls on 9-13 floors in Section III was completed;
- The masonry of the external walls on 14 floors in section III continues;
- The masonry of internal partitions on 9-13 floors in section III continues;
- The installation of ventilation ducts in section I was completed.
/