Construction progress of the CENTRAL HILLS as of June 2026:

У Slate Tower:

  • Monolithic works are being carried out at the 18th floor level;
  • Concreting of the wall and two elevator shafts was carried out with a total concreting volume of 17.6 m³;
  • Work is also underway to monolithicize the areas around the ventilation units on the 14th and 15th floors.

У Ruby Tower:

  • Work is underway to lay the internal partitions and niches on the 25th floor.
/