Feel House CONSTRUCTION PROGRESS - March 2025[:] - LEV Development (Лев Девелопмент)

Feel House CONSTRUCTION PROGRESS – March 2025

March 2025
31

As of March 2025:

  • Roof insulation of 2-4 sections has been completed;
  • The installation of the parapet cover in the courtyard has been completed;
  • Electrical installation work in the parking lot has been completed;
  • Installation of an industrial floor in the parking lot has begun.
/