In December 2021:
- Performed masonry walls 1-3 floors of the I section;
- Completed concrete work 3-4 floors of section II;
- The masonry of the walls of the 1st floor of the III section began;
- Completed concrete work on the 3rd floor of Section III;
- Concrete works of the 4th floor of the III section have begun;
- Completed concrete work 1-2 floors of section IV;
- Concrete work on the 3rd floor of Section IV has begun.
/