Actual news for December from the FEEL HOUSE residential complex construction site in Lviv:
In the I section:
- Facade works continue.
In II-III sections:
- Masonry of partitions of 3-4 floors is finished;
- Work continues on wooden roof structures and installation of metal roofing sheets;
- Installation of windows on 4-5 floors has begun.
In the IV section:
- Masonry of the partitions of 3-4 floors has been completed;
- Masonry of the ventilation ducts and chimneys of the 6th floor has been completed;
- Installation of metal roof structures has been completed;
- A monolithic staircase to the 6th floor was made.