Construction progress of FEEL HOUSE – December 2022

January 2023
05

Actual news for December from the FEEL HOUSE residential complex construction site in Lviv:

In the I section:

  • Facade works continue.

In II-III sections:

  • Masonry of partitions of 3-4 floors is finished;
  • Work continues on wooden roof structures and installation of metal roofing sheets;
  • Installation of windows on 4-5 floors has begun.

In the IV section:

  • Masonry of the partitions of 3-4 floors has been completed;
  • Masonry of the ventilation ducts and chimneys of the 6th floor has been completed;
  • Installation of metal roof structures has been completed;
  • A monolithic staircase to the 6th floor was made.
/