In August 2022:
In the 1st section:
- On the 6th floor (brickwork of ventilation ducts; installation of chimney blocks; installation of wooden roof structures);
- The installation of sewer pipes on all floors has been completed.
- Concreting of the stairs from the 5th to the 6th floor has been completed.
In 2-3 sections:
- Installation of metal channels under the roof structure has been completed;
- Masonry of ventilation ducts and installation of chimneys on the 6th floor has begun;
- Masonry of the gables of the 6th floor has begun.
In the 4th section:
- Masonry of the external walls of the 5th floor has been completed.