Construction progress of FEEL HOUSE – August 2022

August 2022
26

In August 2022:

In the 1st section:

  • On the 6th floor (brickwork of ventilation ducts; installation of chimney blocks; installation of wooden roof structures);
  • The installation of sewer pipes on all floors has been completed.
  • Concreting of the stairs from the 5th to the 6th floor has been completed.

In 2-3 sections:

  • Installation of metal channels under the roof structure has been completed;
  • Masonry of ventilation ducts and installation of chimneys on the 6th floor has begun;
  • Masonry of the gables of the 6th floor has begun.

In the 4th section:

  • Masonry of the external walls of the 5th floor has been completed.
/