Construction progress of HYGGE - December 2020 - LEV Development

Construction progress of HYGGE – December 2020

January 2021
06

In December 2020:

  • Completed laying of interior walls in -2 parking lots;
  • Work on plumbing in -1 level of parking continued;
  • Facade works in the 2nd and completed in the 3rd section are completed, insert 2-3;
  • Installation of electricity in the 3rd section is completed;
  • Landscaping near the 3rd section;
  • Completed waterproofing of the roof (2nd layer);
  • Plastering of internal walls on the 5th floor in the 3rd section is completed;
  • Railings and balcony railings have been installed in 2-3 sections.