Хід будівництва ЖК HYGGE lux - CONSTRUCTION PROGRESS OF THE HYGGE LUX – August 2025 - LEV Development (Лев Девелопмент)

CONSTRUCTION PROGRESS OF THE HYGGE LUX – August 2025

September 2025
03

As of August 2025:

Section IV:

  • We have completed the installation of mirrors in the entrance.
  • We are completing the waterproofing of balconies
  • We are completing the installation of chipboard panels in the entrance.

Section V:

  • We have completed the installation of ceramic tiles on the terraces.
  • The waterproofing of the balconies has been completed.
  • We have completed the installation of mirrors in the entrance hall.

Section VI:

  • We have completed the installation of mirrors in the entrance hall.
  • We are finishing the installation of chipboard panels
  • We have completed the installation of ceramic tiles in the entrance.

Parking:

  • Preparations for pouring the industrial floor have begun.
/