As of May 2024:
- Section IV:
- The painting of the walls in the stairwells and common corridors has been completed;
- The installation of MDF and chipboard plates on the walls is being completed;
- The connection of the general lighting of the MZK has been completed.
- Section IV:
- The brickwork of the walls of the 1st residential floor is 100% completed;
- The brickwork of the walls of the 2nd residential floor is 50% completed
- Partitions of the 1st residential floor are 100% completed.
- Section V:
- The brickwork of the walls of all residential floors is 100% completed;
- The brickwork of partitions on all floors is 90% complete.
- Section VI:
- Windows are being installed on the 4th-6th residential floor;
- The arrangement of the screed on the roof has been completed.