Хід будівництва ЖК HYGGE lux - CONSTRUCTION PROGRESS OF THE HYGGE LUX – MAY 2023 - LEV Development (Лев Девелопмент)

CONSTRUCTION PROGRESS OF THE HYGGE LUX – MAY 2023

May 2024
21

As of May 2024:

  • Section IV:
    • The painting of the walls in the stairwells and common corridors has been completed;
    • The installation of MDF and chipboard plates on the walls is being completed;
    • The connection of the general lighting of the MZK has been completed.

 

  • Section IV:
    • The brickwork of the walls of the 1st residential floor is 100% completed;
    • The brickwork of the walls of the 2nd residential floor is 50% completed
    • Partitions of the 1st residential floor are 100% completed.

 

  • Section V:
    • The brickwork of the walls of all residential floors is 100% completed;
    • The brickwork of partitions on all floors is 90% complete.

 

  • Section VI:
    • Windows are being installed on the 4th-6th residential floor;
    • The arrangement of the screed on the roof has been completed.
/