In June 2021:
- Completed the installation of window structures in section IV;
- 80% of screeds were filled in section I;
- Completed plastering works of the I section;
- Plastering works in sections II and III have started;
- Completed the installation of the heating system of the I section;
- Completed the facade work of the house by 60%.
/