Construction progress of OBRIY 3 - November 2021 - LEV Development

Construction progress of OBRIY 3 – November 2021

November 2021
30

In November 2021:

  • Completed pouring screeds in sections III and IV;
  • Completed the installation of the heating system of section IV;
  • Installation of handrails on balconies of I and II sections was completed;
  • 50% of handrails were installed on the balconies of section III;
  • Completed plastering of walls in sections II and III;
  • 80% of tiles were laid in public places of Section II;
  • Completed laying of tiles in public places of the I section;
  • Performed waterproofing on balconies in all sections.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT
запис на консультацію