In November 2021:
- Completed pouring screeds in sections III and IV;
- Completed the installation of the heating system of section IV;
- Installation of handrails on balconies of I and II sections was completed;
- 50% of handrails were installed on the balconies of section III;
- Completed plastering of walls in sections II and III;
- 80% of tiles were laid in public places of Section II;
- Completed laying of tiles in public places of the I section;
- Performed waterproofing on balconies in all sections.
/