Construction progress of OBRIY 3 - October 2021 - LEV Development

Construction progress of OBRIY 3 – October 2021

November 2021
01

In October 2021:

  • Work has begun on the decoration of common areas in Section II;
  • Completed pouring screeds in section II;
  • 70% of screeds are flooded in section III;
  • Completed plastering works of the IV section;
  • 80% of the heating system of section IV was installed;
  • Installed electricity metering cabinets in all sections;
  • Installation of handrails on balconies of I, II and III sections continues;
/