As of June 2026 :
Section V:
- Improvements are underway on the north side of the entrance;
- Doors have been installed in the cells.
Section VI:
- The pouring of the industrial floor in the parking lot has been completed;
- Improvements are underway on the north side of the entrance.
Section VII:
- The concreting of the industrial floor in the parking lot has been completed;
- The installation of tiles in the MZK has been completed;
- The upper trims of the apartment doors have been installed;
- Painting of walls and ceilings in the MZK is being carried out;
- Improvements are underway near the entrance.
Section VIII:
- The concreting of the industrial floor in the parking lot has been completed;
- Painting work is 90% complete;
- Installation of platbands on apartment doors is underway;
- Improvements are underway near the entrance.
Section IX:
- Doors have been installed in the cells.