In December 2022:
- Masonry of the outer walls of the 1st and 2nd floors of the 1st section was completed;
- The foundation cushion of the II section (1 entrance) is arranged;
- The walls of the parking lot in the II section (1 entrance) have been installed;
- Completed floor slab above the II section parking lot (1 entrance);
- The monolithic walls and columns of the 1st floor of the II section were arranged;
- The floor slab above the 1st floor of the II section is arranged.