In November 2023:
- In the I section:
- Mounted elevators;
- Lined ceramic tiles in the corridors of floors 7-6;
- Facade work continued.
- In the II section:
- The plastering of the walls of floors 2-7 has been completed;
- The semi-dry screed of 6-7 floors has been completed;
- Facade work continued;
- An elevator has been installed;
- Laying of external networks (sewerage) continued.
- In the III section:
- Heating and water supply is 100% completed;
- Electric cables to apartments are 100% laid;
- The laying of low-current networks has been completed by 100%;
- Plastering of the walls of floors 3-6 was completed;
- Facade work continued.
- In the IV section:
- Windows installed at 100%;
- Partition walls are completely bricked;
- Heating and water supply of apartments is 100% completed;
- The laying of low-current networks has been completed in full;
- Electric cables are laid to the apartments on floors 2-5.
- In the V section:
- Masonry of the facade walls is 99% completed;
- Masonry of internal walls and partitions is 60% completed;
- Insulation of the roof with side screeds was made, gluing of 1 layer of roofing material was started;
- Installation of window structures has begun.
- In the VI section:
- The foundation slab is concreted.
- In Section IX:
- We are reinforcing the floor slab of the 7th floor;
- We are building the outer walls of the 1st, 2nd, and 3rd floors.
- Parking between V and IX sections:
- Monolithic works are 75% completed.