PERFECT LIFE CONSTRUCTION PROGRESS - AUGUST 2023[:] - LEV Development (Лев Девелопмент)

PERFECT LIFE CONSTRUCTION PROGRESS – AUGUST 2023

August 2023
15

In August 2023:

  • In the I section:
    • Works on insulation of facades were carried out;
    • Work on plastering the walls of the 8th floor has begun.

 

  • In II, III, IV sections:
    • Masonry of internal walls and partitions on floors 1-6 is in progress;
    • Work has begun on the installation of windows.

 

  • In V, VI sections:
    • A slab above the 2nd floor is arranged.

 

  • In Section IX:
    • They started digging the pit.
/