In January 2023:
- Masonry of the external walls of the 1st-6th floors of the 1st section was completed;
- Masonry of the internal walls and partitions of the 2nd floor of the 1st section was completed;
- Excavation of the pit under the foundation slab of commercial premises (schools) took place;
- The installation of the sub-concrete under the foundation slab (of the school) took place;
- A floor slab was installed above the 1st floor of the 1st entrance of the II section;
- Arranged monolithic columns and walls of the 2nd floor of the 2nd entrance of the II section.