SILENT PARK CONSTRUCTION PROGRESS - JULY 2023[:] - LEV Development (Лев Девелопмент)

SILENT PARK CONSTRUCTION PROGRESS – JULY 2023

July 2024
08

As of July 2024:

House 1:

  • Finished painting the walls;
  • The waterproofing of the terraces has been completed.

 

House 2:

  • Putty works are 80% finished.

 

House 3:

  • The waterproofing of the terraces has begun;
  • Finished plasterboard works;
  • The laying of tiles in the halls is 50% complete;
  • Improvement works are continuing between the 1st and 2nd buildings.

 

House 4:

  • The installation of the heating and water supply system from the 2nd to the 5th floor has been completed;
  • The facade works are 90% complete.

 

House 5:

  • Plastering works are 50% completed;
  • Elevators are being installed;
  • The installation of window structures has been completed;
  • Facade works are being carried out;
  • The installation of the electrical supply to the apartments and the lighting was completed;
  • The -2nd floor of the parking lot between the 5th and 6th sections has been concreted.

 

House 6:

  • Completed monolithic works on the house;
  • We build external walls and partitions from the 1st to the 4th floor.
/