As of July 2024:
House 1:
- Finished painting the walls;
- The waterproofing of the terraces has been completed.
House 2:
- Putty works are 80% finished.
House 3:
- The waterproofing of the terraces has begun;
- Finished plasterboard works;
- The laying of tiles in the halls is 50% complete;
- Improvement works are continuing between the 1st and 2nd buildings.
House 4:
- The installation of the heating and water supply system from the 2nd to the 5th floor has been completed;
- The facade works are 90% complete.
House 5:
- Plastering works are 50% completed;
- Elevators are being installed;
- The installation of window structures has been completed;
- Facade works are being carried out;
- The installation of the electrical supply to the apartments and the lighting was completed;
- The -2nd floor of the parking lot between the 5th and 6th sections has been concreted.
House 6:
- Completed monolithic works on the house;
- We build external walls and partitions from the 1st to the 4th floor.