In November 2023:
House 1:
- Installation of parapets is finished;
- The facade is 90% complete;
- Arranged screeds of 2-5 floors of entrance #1;
- The sewage networks of floors 1-5 have been installed;
- Insulation is installed on the floor of the 1st floor.
House 2:
- The installation of internal electrical networks has been completed;
- Works on installation of water supply and heating systems have been completed by 90%;
- Facade work is 60% completed;
- Plastering works are 70% completed.
House 3:
- Facade work is 25% completed;
- Installation of low-current networks is carried out;
- Work has begun on the roof of the ventilation systems.
Parking:
- Masonry of cells -1 level of the parking lot has begun;
- Works are being carried out on drainage of the parking lot roof;
- Monolithic works are being carried out on the stylobate part of commerce.