SILENT PARK CONSTRUCTION PROGRESS - NOVEMBER 2023[:] - LEV Development (Лев Девелопмент)

SILENT PARK CONSTRUCTION PROGRESS – NOVEMBER 2023

November 2023
16

In November 2023:

House 1:

  • Installation of parapets is finished;
  • The facade is 90% complete;
  • Arranged screeds of 2-5 floors of entrance #1;
  • The sewage networks of floors 1-5 have been installed;
  • Insulation is installed on the floor of the 1st floor.

House 2:

  • The installation of internal electrical networks has been completed;
  • Works on installation of water supply and heating systems have been completed by 90%;
  • Facade work is 60% completed;
  • Plastering works are 70% completed.

House 3:

  • Facade work is 25% completed;
  • Installation of low-current networks is carried out;
  • Work has begun on the roof of the ventilation systems.

Parking:

  • Masonry of cells -1 level of the parking lot has begun;
  • Works are being carried out on drainage of the parking lot roof;
  • Monolithic works are being carried out on the stylobate part of commerce.
/