SILENT PARK CONSTRUCTION PROGRESS – August 2025

August 2025
27

As of August 2025:

  • The installation of glass partitions on the terraces of the 5th building has been completed;
  • We completed the installation of stairwell railings in buildings 4, 5, and 6;
  • Installation of light lantern enclosures on stylobates is underway;
  • Improvement works are 90% complete;
  • Finishing work in the 6th building is 30% complete;
  • Installation of wooden panels has begun in the 4th building.
/