SILENT PARK CONSTRUCTION PROGRESS - January 2022[:] - LEV Development (Лев Девелопмент)

SILENT PARK CONSTRUCTION PROGRESS – January 2022

January 2023
26

In January 2023:

House 1:

  • Masonry of the external walls of the 1st, 2nd, 3rd, 4th and 5th floors is being done.

House 2:

  • Masonry of the walls, columns and floor covering of the 1st floor has been completed;
  • Masonry of the walls and columns of the 2nd floor has begun;
  • The staircases of floors -2, -1 and 1 are concreted.
/