In September 2022:
- The second half of the walls and columns of the 1st floor of the 1st building has been completed;
- The floor slab of the 1st floor of the 1st building was concreted;
- The walls and columns of the 2nd floor have been completed and the floor slab of the 2nd floor of the 1st building has been concreted;
- The foundation slab II of the building was poured.