In September 2023:
House 1:
- Work is being carried out on the laying of internal power grids and low-current networks;
- Finished masonry of interior partitions;
- The ventilation ducts were covered;
- Works on water supply and heating are being carried out;
- The pit is being backfilled.
House 2:
- We are finishing the installation of windows in the first entrance;
- The walls of the 3rd and 5th floors are being laid;
- Preparatory work on the arrangement of the facade is being carried out;
- Balconies and terraces are waterproofed.
House 3:
- Masonry of walls is being carried out on all floors;
- Work on the ventilation system is 80% completed;
- Measurement of window structures was carried out.
Parking:
- Half of the last parking slab between buildings 1 and 2 has been poured;
- Half of the foundations between the 2nd and 3rd buildings have been poured.