SILENT PARK CONSTRUCTION PROGRESS - SEPTEMBER 2023[:] - LEV Development (Лев Девелопмент)

SILENT PARK CONSTRUCTION PROGRESS – SEPTEMBER 2023

September 2023
12

In September 2023:

House 1:

  • Work is being carried out on the laying of internal power grids and low-current networks;
  • Finished masonry of interior partitions;
  • The ventilation ducts were covered;
  • Works on water supply and heating are being carried out;
  • The pit is being backfilled.

House 2:

  • We are finishing the installation of windows in the first entrance;
  • The walls of the 3rd and 5th floors are being laid;
  • Preparatory work on the arrangement of the facade is being carried out;
  • Balconies and terraces are waterproofed.

House 3:

  • Masonry of walls is being carried out on all floors;
  • Work on the ventilation system is 80% completed;
  • Measurement of window structures was carried out.

Parking:

  • Half of the last parking slab between buildings 1 and 2 has been poured;
  • Half of the foundations between the 2nd and 3rd buildings have been poured.
/