Construction progress of Soul Park – March 2025 - LEV Development (Лев Девелопмент)

Construction progress of Soul Park – March 2025

March 2025
06

As of March 2025:

1 section:

  • Work on installing the foundations of the stylobate and transformer substation has been completed.
  • Work is underway to install the walls of the transformer substation and bored piles.

Section 3:

  • Work on installing the foundations of the stylobate has been completed.
  • Excavators are digging a pit for the foundation slab.

Section 4:

  • Work is underway to install the foundation slab.

Section 5:

  • Work on installing parking walls and columns has been completed.
  • Work has begun on installing the parking lot floor slab.
/