As of March 2025:
1 section:
- Work on installing the foundations of the stylobate and transformer substation has been completed.
- Work is underway to install the walls of the transformer substation and bored piles.
Section 3:
- Work on installing the foundations of the stylobate has been completed.
- Excavators are digging a pit for the foundation slab.
Section 4:
- Work is underway to install the foundation slab.
Section 5:
- Work on installing parking walls and columns has been completed.
- Work has begun on installing the parking lot floor slab.