As of December 2025 :
Section 1:
- Work on installing the slope-forming screed on the terrace has been completed.
Section 2:
- Work is underway to install brickwork on the walls and partitions of the 3rd floor;
- Work is underway to install brickwork on the walls and partitions of the 4th floor;
- Work on the installation of ventilation and air conditioning systems has been completed.
Section 3:
- Work on the construction of vertical reinforced concrete structures of walls and columns of the 5th floor has been completed;
- Work on the installation of the 5th floor floor slab has been completed;
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 6th floor;
- Work is underway to install brickwork on the walls and partitions of the 2nd floor;
- Work is underway to install ventilation and air conditioning systems.
Section 4:
- Work on the installation of vertical reinforced concrete roof structures has been completed;
- Work is underway to install ventilation and air conditioning systems;
- Work is underway to install brickwork on the walls and partitions of the 3rd floor;
- Work is underway to install brickwork on the walls and partitions of the 4th floor;
- Work on the installation of the floor slab of the stylobate parking lot on the -2nd floor has been completed;
- Work on the construction of vertical reinforced concrete structures of walls and columns of the 2nd floor of the stylobate has been completed;
- Work on the installation of the floor slab of the 2nd floor of the stylobate has been completed;
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 1st floor of the stylobate.
Section 5:
- Work is underway to plaster the walls of common corridors and staircases;
- Work is underway to install insulation for facades;
- Work is underway to install roof waterproofing;
- Work is underway to install windows and doors to the facade.
Section B8:
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 2nd floor.
Section B7:
- Work on the construction of vertical reinforced concrete structures of the parking lot walls and columns has been completed;
- Work is underway to install the parking lot floor slab.
Section B6:
- Work on the foundation slab has been completed;
- Work is underway to install vertical reinforced concrete structures for the parking lot walls and columns.
Section B5:
- Work on the foundation slab has been completed;
- Work is underway to install the foundations of the stylobate.
Section B4:
- Work is underway to install the foundation slab.
Section B3:
- Work on the arrangement of excavation by excavators has been completed;
- Work on the foundation slab has been completed;
- Work is underway to install the foundations of the stylobate.