Construction progress of Soul Park – December 2025 - LEV Development (Лев Девелопмент)

Construction progress of Soul Park – December 2025

December 2025
23

As of December 2025 :

Section 1:

  • Work on installing the slope-forming screed on the terrace has been completed.

Section 2:

  • Work is underway to install brickwork on the walls and partitions of the 3rd floor;
  • Work is underway to install brickwork on the walls and partitions of the 4th floor;
  • Work on the installation of ventilation and air conditioning systems has been completed.

Section 3:

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 5th floor has been completed;
  • Work on the installation of the 5th floor floor slab has been completed;
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 6th floor;
  • Work is underway to install brickwork on the walls and partitions of the 2nd floor;
  • Work is underway to install ventilation and air conditioning systems.

Section 4:

  • Work on the installation of vertical reinforced concrete roof structures has been completed;
  • Work is underway to install ventilation and air conditioning systems;
  • Work is underway to install brickwork on the walls and partitions of the 3rd floor;
  • Work is underway to install brickwork on the walls and partitions of the 4th floor;
  • Work on the installation of the floor slab of the stylobate parking lot on the -2nd floor has been completed;
  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 2nd floor of the stylobate has been completed;
  • Work on the installation of the floor slab of the 2nd floor of the stylobate has been completed;
  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 1st floor of the stylobate.

Section 5:

  • Work is underway to plaster the walls of common corridors and staircases;
  • Work is underway to install insulation for facades;
  • Work is underway to install roof waterproofing;
  • Work is underway to install windows and doors to the facade.

Section B8:

  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 2nd floor.

Section B7:

  • Work on the construction of vertical reinforced concrete structures of the parking lot walls and columns has been completed;
  • Work is underway to install the parking lot floor slab.

Section B6:

  • Work on the foundation slab has been completed;
  • Work is underway to install vertical reinforced concrete structures for the parking lot walls and columns.

Section B5:

  • Work on the foundation slab has been completed;
  • Work is underway to install the foundations of the stylobate.

Section B4:

  • Work is underway to install the foundation slab.

Section B3:

  • Work on the arrangement of excavation by excavators has been completed;
  • Work on the foundation slab has been completed;
  • Work is underway to install the foundations of the stylobate.
/