Construction progress of Soul Park – November 2025 - LEV Development (Лев Девелопмент)

Construction progress of Soul Park – November 2025

November 2025
21

As of November 2025 :

1 section

  • Work on the installation of vertical monolithic reinforced concrete roof structures has been completed;
  • Work on the brickwork of the walls and partitions of the 5th and 6th floors has been completed;
  • Installation of sewer risers and roof drainage has been completed.

Section 2

  • Work is underway to install vertical monolithic reinforced concrete roof structures;
  • Work is underway to install brickwork on the walls and partitions of the 2nd floor.

Section 3

  • Work on the installation of vertical structures of walls and columns of the 4th floor has been completed;
  • Work on the installation of the 3rd floor floor slab has been completed;
  • Work on the installation of vertical structures of walls and columns of the 4th floor has been completed;
  • Work has begun on installing the 4th floor floor slab.

Section 4

  • Work on the construction of vertical reinforced concrete structures of walls and columns of the 5th floor has been completed;
  • Work on the installation of the 5th floor floor slab has been completed;
  • Work is underway to install vertical reinforced concrete roof structures;
  • Work is underway to install brickwork on the walls and partitions of the 3rd floor.

Section 5

  • Work on the installation of vertical reinforced concrete roof structures has been completed;
  • Work on the brickwork of the walls and partitions of the 5th floor has been completed;
  • Work is underway to install brickwork on the walls and partitions of the 6th floor;
  • Work is underway to install a slope-forming screed on the roof;
  • The installation of sewer risers and roof drainage has been completed.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT