As of November 2025 :
1 section
- Work on the installation of vertical monolithic reinforced concrete roof structures has been completed;
- Work on the brickwork of the walls and partitions of the 5th and 6th floors has been completed;
- Installation of sewer risers and roof drainage has been completed.
Section 2
- Work is underway to install vertical monolithic reinforced concrete roof structures;
- Work is underway to install brickwork on the walls and partitions of the 2nd floor.
Section 3
- Work on the installation of vertical structures of walls and columns of the 4th floor has been completed;
- Work on the installation of the 3rd floor floor slab has been completed;
- Work on the installation of vertical structures of walls and columns of the 4th floor has been completed;
- Work has begun on installing the 4th floor floor slab.
Section 4
- Work on the construction of vertical reinforced concrete structures of walls and columns of the 5th floor has been completed;
- Work on the installation of the 5th floor floor slab has been completed;
- Work is underway to install vertical reinforced concrete roof structures;
- Work is underway to install brickwork on the walls and partitions of the 3rd floor.
Section 5
- Work on the installation of vertical reinforced concrete roof structures has been completed;
- Work on the brickwork of the walls and partitions of the 5th floor has been completed;
- Work is underway to install brickwork on the walls and partitions of the 6th floor;
- Work is underway to install a slope-forming screed on the roof;
- The installation of sewer risers and roof drainage has been completed.