Construction progress of Soul Park – February 2025 - LEV Development (Лев Девелопмент)

Construction progress of Soul Park – February 2025

February 2026
25

As of February 2026  :

Section 1:

  • Work is underway to install windows and doors to the facade.

Section 2:

  • Work is underway to install brickwork on the walls and partitions of the 3rd floor;
  • Work is underway to install brickwork on the walls and partitions of the 4th floor;
  • Work is underway to install drainage risers.

Section 3:

  • Work on the installation of the 6th floor floor slab has been completed;
  • Work is underway to install vertical reinforced concrete roof structures;
  • Work is underway to install brickwork on the walls and partitions of the 2nd floor;
  • Work is underway to install ventilation and air conditioning systems.

Section 4:

  • Work is underway to install brickwork on the walls and partitions of the 4th floor;
  • Work is underway to install brickwork on the walls and partitions of the 5th floor;
  • Work is underway to install drainage and sewer risers.

Section 5:

  • The installation of windows and doors on the facade has been completed;
  • Work is underway to install drainage and sewer risers.

Section B8:

  • Work is underway to install vertical reinforced concrete structures of walls and columns on the 3rd floor.

Section B7:

  • Work on the installation of the 1st floor floor slab has been completed.

Section B6:

  • Work is underway to install vertical reinforced concrete structures for the parking lot walls and columns.

Section B5:

  • Work is underway to install vertical reinforced concrete structures for the parking lot walls and columns.

Section B4:

  • Work is underway to install vertical reinforced concrete structures for the parking lot walls and columns.

Section B3:

  • Work is underway to install vertical reinforced concrete structures for the parking lot walls and columns.

Section B2:

  • Work is underway to install the foundation slab.

Section B1:

  • Work is underway to arrange concrete preparation for the foundation slab.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT