As of February 2026 :
Section 1:
- Work is underway to install windows and doors to the facade.
Section 2:
- Work is underway to install brickwork on the walls and partitions of the 3rd floor;
- Work is underway to install brickwork on the walls and partitions of the 4th floor;
- Work is underway to install drainage risers.
Section 3:
- Work on the installation of the 6th floor floor slab has been completed;
- Work is underway to install vertical reinforced concrete roof structures;
- Work is underway to install brickwork on the walls and partitions of the 2nd floor;
- Work is underway to install ventilation and air conditioning systems.
Section 4:
- Work is underway to install brickwork on the walls and partitions of the 4th floor;
- Work is underway to install brickwork on the walls and partitions of the 5th floor;
- Work is underway to install drainage and sewer risers.
Section 5:
- The installation of windows and doors on the facade has been completed;
- Work is underway to install drainage and sewer risers.
Section B8:
- Work is underway to install vertical reinforced concrete structures of walls and columns on the 3rd floor.
Section B7:
- Work on the installation of the 1st floor floor slab has been completed.
Section B6:
- Work is underway to install vertical reinforced concrete structures for the parking lot walls and columns.
Section B5:
- Work is underway to install vertical reinforced concrete structures for the parking lot walls and columns.
Section B4:
- Work is underway to install vertical reinforced concrete structures for the parking lot walls and columns.
Section B3:
- Work is underway to install vertical reinforced concrete structures for the parking lot walls and columns.
Section B2:
- Work is underway to install the foundation slab.
Section B1:
- Work is underway to arrange concrete preparation for the foundation slab.