As of September 2025:
Section I:
- The installation of the 4th floor floor slab has been completed;
- The installation of vertical wall and column structures on the 5th floor has been completed;
- The 5th floor slab is being installed;
- The brickwork of the walls and partitions of the 2nd floor has been completed;
- The brickwork of the walls and partitions of the 3rd floor is being installed.
Section II:
- The installation of vertical wall and column structures on the 4th floor has been completed;
- The installation of the 4th floor floor slab has been completed;
- The vertical structures of the walls and columns of the 5th floor are being installed;
- The brickwork of the walls and partitions of the 2nd floor is being installed.
Section III:
- The installation of vertical wall and column structures on the 1st floor has been completed;
- The 1st floor floor slab is being installed.
Section IV:
- The installation of the 1st floor floor slab has been completed;
- The installation of vertical wall and column structures on the 2nd floor has been completed;
- The installation of the 2nd floor floor slab has been completed;
- The installation of vertical wall and column structures on the 3rd floor has been completed;
- The installation of the 3rd floor floor slab has been completed;
- The vertical structures of the walls and columns of the 4th floor are being installed;
- The brickwork of the walls and partitions of the 2nd floor is being installed.
Section V:
- The installation of vertical wall and column structures on the 4th floor has been completed;
- The installation of the 4th floor floor slab has been completed;
- The installation of vertical wall and column structures on the 5th floor has been completed;
- The installation of the 5th floor floor slab has been completed;
- The installation of vertical wall and column structures on the 6th floor has been completed;
- The 6th floor slab is being installed;
- The brickwork of the walls and partitions of the 2nd floor has been completed;
- The brickwork of the walls and partitions of the 3rd floor is being installed;
- The brickwork of the walls and partitions of the 4th floor is being installed.