As of April 2026:
Section A2:
- We reinforce the foundation slab of the house.
Section A3:
- We have completed the work of concreting the floor slab above the parking lot.
- Waterproofing of parking lot walls completed
- Work is underway to backfill the pit sinuses.
Section A4:
- Concreting of parking lot walls and columns is 100% complete
- Waterproofing of the parking lot walls was done
- Backfilling of the pit sinuses is being carried out.
Section A5:
- We have completed the work of concreting the foundation slab.
- Tower crane installation work underway