Хід будівництва ЖК VERO - Construction progress of the VERO – April 2026 - LEV Development (Лев Девелопмент)

Construction progress of the VERO – April 2026

April 2026
24

As of April 2026:

Section A2:

  • We reinforce the foundation slab of the house.

Section A3:

  • We have completed the work of concreting the floor slab above the parking lot.
  • Waterproofing of parking lot walls completed
  • Work is underway to backfill the pit sinuses.

Section A4:

  • Concreting of parking lot walls and columns is 100% complete
  • Waterproofing of the parking lot walls was done
  • Backfilling of the pit sinuses is being carried out.

Section A5:

  • We have completed the work of concreting the foundation slab.
  • Tower crane installation work underway
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT