As of April 2026:
Section A3:
- Work on the construction of monolithic walls and columns of the 1st floor has been completed;
- Work has begun on the installation of formwork for the 1st floor floor slab.
Section A4:
- The floor slab above the parking lot has been completed;
- We reinforce and concrete the walls and columns of the 1st floor.
Section A5:
- Concrete work was performed to install the walls and columns of the parking lot;
- The formwork for the floor slab above the parking lot has been completed;
- Work has begun on reinforcing the slab.
Section A6:
- The foundation slab is concreted;
- Reinforcement of the columns and walls of the parking lot has begun.
Stylobate between sections A5 and A6:
- Concreting of parking columns has been completed.