Хід будівництва ЖК VERO - Construction progress of the VERO – May 2026 - LEV Development (Лев Девелопмент)

Construction progress of the VERO – May 2026

May 2026
19

As of April 2026:

Section A3:

  • Work on the construction of monolithic walls and columns of the 1st floor has been completed;
  • Work has begun on the installation of formwork for the 1st floor floor slab.

Section A4:

  • The floor slab above the parking lot has been completed;
  • We reinforce and concrete the walls and columns of the 1st floor.

Section A5:

  • Concrete work was performed to install the walls and columns of the parking lot;
  • The formwork for the floor slab above the parking lot has been completed;
  • Work has begun on reinforcing the slab.

Section A6:

  • The foundation slab is concreted;
  • Reinforcement of the columns and walls of the parking lot has begun.

Stylobate between sections A5 and A6:

  • Concreting of parking columns has been completed.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT