In April 2021:
- The installation of aluminum structures in the atrium was completed and the installation of double-glazed windows began;
- Sewage pipes continued to be built;
- Installation of gypsum cardboard on partitions between numbers on 2-6 floors proceeded;
- Installation of the water supply system has begun;
- Installation of aluminum windows continued;
- The installation of the power supply system of the rooms has begun;
- Preparatory work for plastering the walls with gypsum plaster continued.
/