At the end of November 2021:
- Installation of fiber cement boards on the ventilated facade proceeds;
- We continue to putty walls and ceilings on the 3rd and 7th floors;
- Armstrong ceilings have been installed in the bathrooms and corridors of the rooms;
- We put ceramic tiles in the bathrooms;
- Completed the installation of the frame of the suspended ceiling of plasterboard on the ground floor;
- We install ceramic tiles in the bathrooms;
- Installation of the air conditioning system continues.
/