At the end of November 2021:
Section 1
- The masonry of vertical structures (pylons, walls) of the 11th floor has been completed.
- Ventilation units are mounted on the 7th
Section 2
- The floor covering of the 14th floor has been completed.
- 55% of vertical structures (pylons, walls) of the 15th floor are concreted.
- 10% masonry of the 8th floor of external and internal walls is made.
- The masonry of the 7th floor of the external and internal walls has been completed.
- Ventilation ducts have been installed on the 10th floor.
/