In February 2021:
- Installation and connection of plumbing installations on 2-5 floors is completed.
- Installation of plasterboard partition frames on the 6th floor continued.
- Work continued on the arrangement of the acoustic mine in the partitions between the rooms on 2-5 floors.
- Installation of aluminum windows has begun.
- Preparatory work for the insulation of the facade continued.