Construction progress of LEV CITY HOTEL – February 2021

March 2021
04

In February 2021:

  • Installation and connection of plumbing installations on 2-5 floors is completed.
  • Installation of plasterboard partition frames on the 6th floor continued.
  • Work continued on the arrangement of the acoustic mine in the partitions between the rooms on 2-5 floors.
  • Installation of aluminum windows has begun.
  • Preparatory work for the insulation of the facade continued.